Pennsylvania data center energy laws: 1 recorded action
- HB 1834 (2025 to 2026 session): Data center ratepayer protection billpassed one chamber, 2026
Passed the House 104 to 95 on March 24, 2026 and awaits Senate action; establishes a new rate class for data centers of 25 MW or more and prohibits public utilities from shifting the costs of new generation and transmission infrastructure built for data centers onto other ratepayers.
Binds: Pennsylvania public utilities, the PUC, and data centers of 25 MW or more. Verified September 10, 2026 against the official source.
Questions
- What has Pennsylvania done about data center energy?
- 1 recorded action as of September 10, 2026: HB 1834 (2025 to 2026 session) (passed one chamber, 2026). Each record below links the official source.
Part of the US AI Energy Policy Tracker. Coverage is what could be verified against official sources, not a claim to be exhaustive.