Virginia data center energy laws: 1 recorded action
Approved March 24, 2025; directs the State Corporation Commission to determine whether Dominion Energy and Appalachian Power use reasonable customer classifications, including whether a new or separate classification for data center customers is warranted; in November 2025 the SCC approved a new Dominion rate class for customers above 25 MW with minimum demand payments and long-term contracts.
Binds: Virginia State Corporation Commission, Dominion Energy, and Appalachian Power; affects data center customers. Verified September 10, 2026 against the official source.
Questions
- What has Virginia done about data center energy?
- 1 recorded action as of September 10, 2026: HB 2084 (2025) (enacted, 2025). Each record below links the official source.
Part of the US AI Energy Policy Tracker. Coverage is what could be verified against official sources, not a claim to be exhaustive.