China set a national data centre efficiency target and a renewables ramp
A special action plan jointly issued in July 2024 by the National Development and Reform Commission, the Ministry of Industry and Information Technology and two central bureaus set an average power usage effectiveness for data centres of below 1.5 by 2025 and an increase in the renewable energy utilisation rate of 10 percent a year.
The verdict
Verified
The document exists. The ledger fetched it at its publisher and quotes it.
Key facts
What the sources say
- Record ID
- AIA-2026-0027
- Kind
- Reporting and efficiency duties
- Jurisdiction
- China
- Last verified
- Added
- The plan sets an average power usage effectiveness for data centres of less than 1.5 by 2025.
- It aims to increase the utilisation rate of renewable energy in data centres by 10 percent annually.
- It was issued jointly by the National Development and Reform Commission, the Ministry of Industry and Information Technology and two central bureaus.
- The figures come from the Chinese government's own English language service, published 24 July 2024.
- Reported claims of a tighter target of 1.25 for large data centres were not reachable at a Chinese government primary and are not printed here as verified.
Figures
Every number, with who measured it and when
- 1.5 PUE ratio
Average data centre power usage effectiveness target for 2025
The State Council of the People's Republic of China, China sets green targets for data centers, primary source, as of .
- 10 percent per year
Annual increase in renewable energy utilisation rate set by the plan
The State Council of the People's Republic of China, China sets green targets for data centers, primary source, as of .
What it changes
For an operator, a utility or a community
An operator comparing efficiency regimes should note that China set a national average rather than a per site ceiling, which is a different instrument from the German statute. A utility should read the renewables ramp as the binding half of the plan. A community outside China still has a use for this row: it is the benchmark other governments cite when they argue their own targets are modest.
Sources
What this record was verified against
Related
Records that sit beside this one
East Data West Computing moves Chinese compute to where the power is
China · verified 15 September 2026
The project launched in 2022 and routes data produced in eastern provinces to facilities in western China.
Measured efficiency has not moved: a weighted average PUE of 1.54
Global · verified 15 September 2026
The weighted average annual PUE reported by respondents in 2025 was 1.54.
Cite this record
Free to reuse under CC BY 4.0, with attribution. The record ID AIA-2026-0027 is permanent and is never reused.
- In a sentence
- According to the GAGE AI Infrastructure Atlas (as of 15 September 2026), china set a national data centre efficiency target and a renewables ramp.
- APA
- GAGE (Global Academy of Generative-AI Education). (2026). China set a national data centre efficiency target and a renewables ramp. AI Infrastructure Atlas. Retrieved 15 September 2026, from https://www.gage.academy/tools/ai-infrastructure-atlas/records/AIA-2026-0027-china-green-low-carbon-data-centre-plan
- MLA
- "China set a national data centre efficiency target and a renewables ramp." AI Infrastructure Atlas, GAGE (Global Academy of Generative-AI Education), 15 September 2026, https://www.gage.academy/tools/ai-infrastructure-atlas/records/AIA-2026-0027-china-green-low-carbon-data-centre-plan.
- Chicago
- GAGE (Global Academy of Generative-AI Education). "China set a national data centre efficiency target and a renewables ramp." AI Infrastructure Atlas. Last modified 15 September 2026. https://www.gage.academy/tools/ai-infrastructure-atlas/records/AIA-2026-0027-china-green-low-carbon-data-centre-plan.
- Permalink
- https://www.gage.academy/tools/ai-infrastructure-atlas/records/AIA-2026-0027-china-green-low-carbon-data-centre-plan
Last updated . Every record re verified . The ledger is checked monthly, first Monday, and the same day for any regulator decision on large loads or water.
Back to the full ledger, or every record for China and every reporting and efficiency duties record.
GAGE briefings tell you which AI regulation deadlines are coming, what they actually require of you, and when a program opens.