Executive Order 14318 puts qualifying data center projects on a federal fast track

Executive Order 14318, signed 23 July 2025, directs federal agencies to speed permitting for data centers and the power and component projects that serve them. A qualifying project is one with at least 500 million dollars of committed capital expenditure or an incremental electric load addition greater than 100 MW, or one designated for national security.

The verdict

Verified

The document exists. The ledger fetched it at its publisher and quotes it.

Key facts

What the sources say

Record ID
AIA-2026-0002
Kind
Siting, permitting and tax
Jurisdiction
United States
Last verified
Added
  • The order names two quantitative routes into qualifying status: committed capital expenditure of at least 500 million dollars, or an incremental electric load addition greater than 100 MW.
  • It directs agencies to establish categorical exclusions covering actions related to qualifying projects that normally do not have a significant effect on the human environment.
  • It reaches data center projects and covered component projects, which include energy infrastructure and semiconductor and networking equipment.
  • The order was published in the Federal Register on 28 July 2025 at 90 FR 35385.

Figures

Every number, with who measured it and when

  1. 500,000,000 US dollars

    Capital expenditure that makes a project qualifying under EO 14318

    The White House, Accelerating Federal Permitting of Data Center Infrastructure, primary source, as of .

  2. 100 MW

    Incremental electric load addition that makes a project qualifying under EO 14318

    The White House, Accelerating Federal Permitting of Data Center Infrastructure, primary source, as of .

What it changes

For an operator, a utility or a community

An operator above either threshold can ask for federal permitting treatment that a smaller project cannot, which changes the calculus on project size and on siting near federal land. A utility serving such a project should expect the federal review to move faster than its own interconnection study. A community should understand that a categorical exclusion removes the full environmental review for the covered action, so the questions that matter locally, water draw and local air quality, move to state and county permits.

Sources

What this record was verified against

  1. The White House, Accelerating Federal Permitting of Data Center InfrastructurePrimary · 23 July 2025
  2. Executive Order 14318, Federal Register volume 90 number 142, GovInfoPrimary · 28 July 2025

Related

Cite this record

Free to reuse under CC BY 4.0, with attribution. The record ID AIA-2026-0002 is permanent and is never reused.

In a sentence
According to the GAGE AI Infrastructure Atlas (as of 15 September 2026), executive order 14318 puts qualifying data center projects on a federal fast track.
APA
GAGE (Global Academy of Generative-AI Education). (2026). Executive Order 14318 puts qualifying data center projects on a federal fast track. AI Infrastructure Atlas. Retrieved 15 September 2026, from https://www.gage.academy/tools/ai-infrastructure-atlas/records/AIA-2026-0002-executive-order-14318-federal-permitting
MLA
"Executive Order 14318 puts qualifying data center projects on a federal fast track." AI Infrastructure Atlas, GAGE (Global Academy of Generative-AI Education), 15 September 2026, https://www.gage.academy/tools/ai-infrastructure-atlas/records/AIA-2026-0002-executive-order-14318-federal-permitting.
Chicago
GAGE (Global Academy of Generative-AI Education). "Executive Order 14318 puts qualifying data center projects on a federal fast track." AI Infrastructure Atlas. Last modified 15 September 2026. https://www.gage.academy/tools/ai-infrastructure-atlas/records/AIA-2026-0002-executive-order-14318-federal-permitting.
Permalink
https://www.gage.academy/tools/ai-infrastructure-atlas/records/AIA-2026-0002-executive-order-14318-federal-permitting

Last updated . Every record re verified . The ledger is checked monthly, first Monday, and the same day for any regulator decision on large loads or water.

Back to the full ledger, or every record for United States and every siting, permitting and tax record.

GAGE briefings tell you which AI regulation deadlines are coming, what they actually require of you, and when a program opens.