EU law: data centres above 500 kW must publish their performance
Article 12 of the Energy Efficiency Directive (EU) 2023/1791 requires Member States, from 15 May 2024 and every year after, to make owners and operators of data centres with installed IT power of at least 500 kW publish the information in Annex VII, and requires the Commission to run a European database of what they report.
The verdict
Verified
The document exists. The ledger fetched it at its publisher and quotes it.
Key facts
What the sources say
- Record ID
- AIA-2026-0012
- Kind
- Reporting and efficiency duties
- Jurisdiction
- European Union
- Last verified
- Added
- The duty attaches at an installed information technology power demand of at least 500 kW.
- Information protected by Union or national law on trade and business secrets is carved out of publication.
- Data centres used exclusively for defence and civil protection are outside Article 12.
- The Commission must establish a European database on data centres, publicly available at an aggregated level.
- Member States must encourage operators at or above 1 MW to follow the European Code of Conduct on Data Centre Energy Efficiency.
- Article 12(5) required the Commission to assess the submitted data by 15 May 2025 and report to the Parliament and Council, with legislative proposals where appropriate, including minimum performance standards.
Figures
Every number, with who measured it and when
- 500 kW
Installed IT power at which the Article 12 duty attaches
Directive (EU) 2023/1791 on energy efficiency, Article 12, EUR-Lex, primary source, as of .
- 1 MW
Installed IT power above which Member States must encourage the Code of Conduct
Directive (EU) 2023/1791 on energy efficiency, Article 12, EUR-Lex, primary source, as of .
What it changes
For an operator, a utility or a community
An operator with a European site above 500 kW is already a reporting entity and does not get to choose. A utility should note that the duty sits on the data centre operator, not on the network, so the numbers it wants may be obtainable from the operator's own filing. A community in an EU Member State should know that aggregated national figures are meant to be public, while the individual site's numbers are not.
Sources
What this record was verified against
- Directive (EU) 2023/1791 on energy efficiency, Article 12, EUR-LexPrimary · 20 September 2023
Related
Records that sit beside this one
The EU data centre reporting scheme: what must be filed, and by when
European Union · verified 15 September 2026
The first filing date was 15 September 2024, and the annual date is 15 May thereafter.
Europe collects site level data centre figures and keeps them confidential
European Union · verified 15 September 2026
The database publishes information, indicators and sustainability indicators in an aggregated manner at Member State and Union level.
The Commission is preparing minimum performance standards for EU data centres
European Union · verified 15 September 2026
The study supports the development of minimum performance standards for data centres in Europe, aligned with existing EU reporting requirements.
Europe's public compute build: 19 AI factories and 13 antennas
European Union · verified 15 September 2026
Nineteen AI factories have been established and thirteen AI factory antennas selected.
The Cloud and AI Development Act proposal ties European compute capacity to energy efficiency
European Union · verified 15 September 2026
The Commission adopted the proposal on 3 June 2026 and it carries the reference COM(2026) 502.
The EU Water Resilience Strategy names data centres and promises water standards
European Union · verified 15 September 2026
The strategy states that the EU should aim to enhance water efficiency by at least 10 percent by 2030.
Cite this record
Free to reuse under CC BY 4.0, with attribution. The record ID AIA-2026-0012 is permanent and is never reused.
- In a sentence
- According to the GAGE AI Infrastructure Atlas (as of 15 September 2026), eu law: data centres above 500 kw must publish their performance.
- APA
- GAGE (Global Academy of Generative-AI Education). (2026). EU law: data centres above 500 kW must publish their performance. AI Infrastructure Atlas. Retrieved 15 September 2026, from https://www.gage.academy/tools/ai-infrastructure-atlas/records/AIA-2026-0012-eu-energy-efficiency-directive-article-12
- MLA
- "EU law: data centres above 500 kW must publish their performance." AI Infrastructure Atlas, GAGE (Global Academy of Generative-AI Education), 15 September 2026, https://www.gage.academy/tools/ai-infrastructure-atlas/records/AIA-2026-0012-eu-energy-efficiency-directive-article-12.
- Chicago
- GAGE (Global Academy of Generative-AI Education). "EU law: data centres above 500 kW must publish their performance." AI Infrastructure Atlas. Last modified 15 September 2026. https://www.gage.academy/tools/ai-infrastructure-atlas/records/AIA-2026-0012-eu-energy-efficiency-directive-article-12.
- Permalink
- https://www.gage.academy/tools/ai-infrastructure-atlas/records/AIA-2026-0012-eu-energy-efficiency-directive-article-12
Last updated . Every record re verified . The ledger is checked monthly, first Monday, and the same day for any regulator decision on large loads or water.
Back to the full ledger, or every record for European Union and every reporting and efficiency duties record.
GAGE briefings tell you which AI regulation deadlines are coming, what they actually require of you, and when a program opens.